A) The proposed new project would increase the firm's corporate risk.
B) The proposed new project would increase the firm's market risk.
C) The proposed new project would not affect the firm's risk at all.
D) The proposed new project would have less stand-alone risk than the firm's typical project.
E) The proposed new project would have more stand-alone risk than the firm's typical project.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) All sunk costs that have been incurred relating to the project.
B) All interest expenses on debt used to help finance the project.
C) The investment in working capital required to operate the project, even if that investment will be recovered at the end of the project's life.
D) Sunk costs that have been incurred relating to the project, but only if those costs were incurred prior to the current year.
E) Effects of the project on other divisions of the firm, but only if those effects lower the project's own direct cash flows.
Correct Answer
verified
Multiple Choice
A) Under current laws and regulations, corporations must use straight-line depreciation for all assets whose lives are 5 years or longer.
B) Corporations must use the same depreciation method (e.g., straight line or accelerated) for stockholder reporting and tax purposes.
C) Since depreciation is not a cash expense, it has no effect on cash flows and thus no effect on capital budgeting decisions.
D) Under accelerated depreciation, higher depreciation charges occur in the early years, and this reduces the early cash flows and thus lowers a project's projected NPV.
E) Using accelerated depreciation rather than straight line would normally have no effect on a project's total projected cash flows but it would affect the timing of the cash flows and thus the NPV.
Correct Answer
verified
Multiple Choice
A) If the building could be sold, then the after-tax proceeds that would be generated by any such sale should be charged as a cost to any new project that would use it.
B) This is an example of an externality, because the very existence of the building affects the cash flows for any new project that Rowell might consider.
C) Since the building was built in the past, its cost is a sunk cost and thus need not be considered when new projects are being evaluated, even if it would be used by those new projects.
D) If there is a mortgage loan on the building, then the interest on that loan would have to be charged to any new project that used the building.
E) Since the building has been paid for, it can be used by another project with no additional cost.Therefore, it should not be reflected in the cash flows for any new project.
Correct Answer
verified
Multiple Choice
A) In a capital budgeting analysis where part of the funds used to finance the project would be raised as debt, failure to include interest expense as a cost when determining the project's cash flows will lead to a downward bias in the NPV.
B) The existence of any type of "externality" will reduce the calculated NPV versus the NPV that would exist without the externality.
C) If one of the assets to be used by a potential project is already owned by the firm, and if that asset could be sold or leased to another firm if the new project were not undertaken, then the net after-tax proceeds that could be obtained should be charged as a cost to the project under consideration.
D) If one of the assets to be used by a potential project is already owned by the firm but is not being used, then any costs associated with that asset is a sunk cost and should be ignored.
E) In a capital budgeting analysis where part of the funds used to finance the project would be raised as debt, failure to include interest expense as a cost when determining the project's cash flows will lead to an upward bias in the NPV.
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) A sunk cost is any cost that was expended in the past but can be recovered if the firm decides not to go forward with the project.
B) A sunk cost is a cost that was incurred and expensed in the past and cannot be recovered if the firm decides not to go forward with the project.
C) Sunk costs were formerly hard to deal with but now that the NPV method is widely used, it is possible to simply include sunk costs in the cash flows and then calculate the PV of the project.
D) A good example of a sunk cost is a situation where Home Depot opens a new store, and that leads to a decline in sales of one of the firm's existing stores.
E) A sunk cost is any cost that must be expended in order to complete a project and bring it into operation.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) An example of an externality is a situation where a bank opens a new office, and that new office causes deposits in the bank's other offices to increase.
B) The NPV method automatically deals correctly with externalities, even if the externalities are not specifically identified, but the IRR method does not.This is another reason to favor the NPV.
C) Both the NPV and IRR methods deal correctly with externalities, even if the externalities are not specifically identified.However, the payback method does not.
D) Identifying an externality can never lead to an increase in the calculated NPV.
E) An externality is a situation where a project would have an adverse effect on some other part of the firm's overall operations.If the project would have a favorable effect on other operations, then this is not an externality.
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) Under current laws and regulations, corporations must use straight-line depreciation for all assets whose lives are 3 years or longer.
B) If firms use accelerated depreciation, they will write off assets slower than they would under straight-line depreciation, and as a result projects' forecasted NPVs are normally lower than they would be if straight-line depreciation were required for tax purposes.
C) If they use accelerated depreciation, firms can write off assets faster than they could under straight-line depreciation, and as a result projects' forecasted NPVs are normally lower than they would be if straight-line depreciation were required for tax purposes.
D) If they use accelerated depreciation, firms can write off assets faster than they could under straight-line depreciation, and as a result projects' forecasted NPVs are normally higher than they would be if straight-line depreciation were required for tax purposes.
E) Since depreciation is not a cash expense, and since cash flows and not accounting income are the relevant input, depreciation plays no role in capital budgeting.
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Showing 1 - 20 of 56
Related Exams