Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) 9.42%
B) 9.91%
C) 10.44%
D) 10.96%
E) 11.51%
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) 9.06%
B) 9.44%
C) 9.84%
D) 10.23%
E) 10.64%
Correct Answer
verified
Multiple Choice
A) 10.85%
B) 11.19%
C) 11.53%
D) 11.88%
E) 12.24%
Correct Answer
verified
Multiple Choice
A) The WACC is calculated on a before-tax basis.
B) The WACC exceeds the cost of equity.
C) The cost of equity is always equal to or greater than the cost of debt.
D) The cost of reinvested earnings typically exceeds the cost of new common stock.
E) The interest rate used to calculate the WACC is the average after-tax cost of all the company's outstanding debt as shown on its balance sheet.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) 1.13%
B) 1.50%
C) 1.88%
D) 2.34%
E) 2.58%
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) Project C, which is of above-average risk and has a return of 11%.
B) Project A, which is of average risk and has a return of 9%.
C) None of the projects should be accepted.
D) All of the projects should be accepted.
E) Project B, which is of below-average risk and has a return of 8.5%.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) become less risky over time, and this will maximize its intrinsic value.
B) accept too many low-risk projects and too few high-risk projects.
C) become more risky and also have an increasing WACC. Its intrinsic value will not be maximized.
D) continue as before, because there is no reason to expect its risk position or value to change over time as a result of its use of a single cost of capital.
E) become riskier over time, but its intrinsic value will be maximized.
Correct Answer
verified
Multiple Choice
A) If a firm's managers want to maximize the value of their firm's stock, they should, in theory, concentrate on project risk as measured by the standard deviation of the project's expected future cash flows.
B) If a firm evaluates all projects using the same cost of capital, and the CAPM is used to help determine that cost, then its risk as measured by beta will probably decline over time.
C) Projects with above-average risk typically have higher than average expected returns. Therefore, to maximize a firm's intrinsic value, its managers should favor high-beta projects over those with lower betas.
D) Project A has a standard deviation of expected returns of 20%, while Project B's standard deviation is only 10%. A's returns are negatively correlated with both the firm's other assets and the returns on most stocks in the economy, while B's returns are positively correlated. Therefore, Project A is less risky to a firm and should be evaluated with a lower cost of capital.
E) If a firm has a beta that is less than 1.0, say 0.9, this would suggest that the expected returns on its assets are negatively correlated with the returns on most other firms' assets.
Correct Answer
verified
Multiple Choice
A) 6.89%
B) 7.26%
C) 7.64%
D) 8.04%
E) 8.44%
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) 7.81%
B) 8.22%
C) 8.65%
D) 9.10%
E) 9.56%
Correct Answer
verified
Showing 41 - 60 of 92
Related Exams